Critical path scheduling

When can the project finish, and which tasks decide that?

Eleven software tasks depend on each other. EyeProlog computes the earliest start and finish of every task, the project’s finish date, and the chain of tasks that leaves no slack. That chain is the critical path, and any delay on it delays the whole project.

Run it in the playground · Source


The question

A task can start only when all of its predecessors have finished. So its earliest start is the latest finish among its predecessors, and its finish is that start plus its own duration.

The project ends when its last task ends. The critical tasks are the ones you reach by walking back from that last task, each time to the predecessor that finished last.


The project network

task(requirements, 2).
task(architecture, 3).
task(api_design, 2).
task(database, 4).
task(backend, 6).

depends(architecture, requirements).
depends(api_design, requirements).
depends(database, architecture).
depends(backend, api_design).
depends(backend, database).

task(Name, Duration) gives a duration in project time units, and depends(Task, Predecessor) is one edge of the network. The full file has eleven tasks and fourteen edges, ending in launch.


The rules

earliest_start(Task, 0) :-
  task(Task, _duration),
  \+ depends(Task, _pred).
earliest_start(Task, Start) :-
  depends(Task, _pred),
  aggregate_max(Finish, Pred,
    (depends(Task, Pred), finish_time(Pred, Finish)),
    Start, _criticalpred).

finish_time(Task, Finish) :-
  task(Task, Duration),
  earliest_start(Task, Start),
  (Finish is Start + Duration).

A task with no predecessors starts at 0. Any other task starts at the maximum predecessor finish, which aggregate_max/5 computes. earliest_start/2 and finish_time/2 are declared with :- table, so each task’s times are computed once and reused by every query that needs them.


The answer

eyeprolog examples/critical-path-schedule.pl
critical_path_answer(project_finish, 23).
critical_path_answer(critical_task, launch).
critical_path_answer(critical_task, security_review).
critical_path_answer(critical_task, integration).
critical_path_answer(critical_task, backend).
critical_path_answer(critical_task, database).
critical_path_answer(critical_task, architecture).
critical_path_answer(critical_task, requirements).
critical_path_answer(schedule, task(requirements, 0, 2)).
critical_path_answer(schedule, task(architecture, 2, 5)).

The project takes 23 units. Seven tasks are critical. The other eleven answers give each task’s start and finish (two are shown here). frontend, auth, api_design, and load_test have slack: they can slip a little without moving the finish date.


The reason

step(project_finish(23),
     rule(32),
     ['Finish' = 23],
     [aggregate_max(Key, Value, finish_time(Value, Key), 23, launch)]).
step(earliest_start(backend, 9),
     rule(29),
     ['Task' = backend, 'Start' = 9],
     [depends(backend, api_design),
      aggregate_max(Key, Value, (depends(backend, Value), finish_time(Value, Key)), 9, database)]).

The project finishes at 23 because the largest finish time belongs to launch. The backend starts at 9 because, of its two predecessors, database finishes last, at 9. That is why database lies on the critical path and api_design does not.


The check

condition('C1', resolution, ok, 105).
condition('C5', re_decision, ok, 11).
condition('C6', boundary_consistency, ok, 1).
obligation(builtin, theory_scoped, aggregate_max(A, B, finish_time(B, A), 23, launch)).
obligation(absent, theory_scoped, \+ depends(requirements, A)).
steps(128).
trusted(12).
verdict(checked_with_obligations).

The checker replays 105 rule and fact steps and recomputes 11 arithmetic steps. Twelve steps are obligations: the eleven maxima and the claim that requirements has no predecessor. A maximum over the program’s own finish_time/2 cannot be recomputed without running the program, so the verdict is checked_with_obligations. The proof is valid provided those twelve conclusions hold, and the file lists every one of them.