A task is done when every one of its subtasks is done.
task-completion.n3 · output · proof · check · try it in the playground
The question
Two composite tasks are broken into subtasks. A status document lists the subtasks of each and marks the completed ones. Task 1 has three subtasks, all completed. Task 2 has two, and the second is not marked completed.
Which composite tasks are completed? That needs a rule that says “for every subtask”, not just “for some subtask”.
What we tell Eyeron
:subtasks :graph {
:task1 :subTask :subtask1 .
:subtask1 a :Completed .
…
:task2 :subTask :subtask4 .
:subtask4 a :Completed .
:task2 :subTask :subtask5 .
# :subtask5 a :Completed.
} .
The status document is a quoted graph in braces: a document held as a value, not facts of the main graph. The commented-out line is there to try.
{
?Task a :CompositeTask .
:subtasks :graph ?Graph .
(
{
?Task :subTask ?Subtask
}
{
?Subtask a :Completed
}
) log:forAllIn ?Graph .
} => {
?Task a :AllTasksCompleted
} .
log:forAllIn takes a pair of patterns and a graph. It holds when, inside
that graph, every match of the first pattern (each subtask of the task) also
satisfies the second (that subtask is completed). This is a universal test,
scoped to one fixed document.
What Eyeron concludes
:task1 a :AllTasksCompleted .
Task 2 is not concluded: subtask 5 is not marked completed.
The proof: a universal test recorded once
{ :task1 a :AllTasksCompleted . }
pe:rule 1;
…
{
({
:task1 :subTask ?Subtask .
} {
?Subtask a :Completed .
}) log:forAllIn {
:task1 :subTask :subtask1 .
:subtask1 a :Completed .
…
} .
}
pe:builtin log:forAllIn.
The “for every subtask” check is a single built-in step that carries the whole document it ran over.
Checked: what the report says
# checked: 4 steps, 4 verified, 0 trusted
pe:condition [ pe:id "C5"; pe:name "re-decision"; pe:checked 1; pe:failed 0 ];
Four steps: the rule step, two facts and the built-in step. C1–C4 confirm
the rule step matches and the argument is complete and not circular; C7
that nothing is padding; C10 that the test was checked as called. C5
re-decision re-runs the log:forAllIn test over the quoted document, so
the “every subtask” claim is recomputed, not taken on trust.
Try it
eyeron examples/task-completion.n3
eyeron -c examples/task-completion.n3
Uncomment :subtask5 a :Completed. (and add a space before the final .):
now both tasks are completed.
Takeaway
“Every subtask is done” is a universal claim; scoped to a fixed document it becomes a test anyone can recompute.