The question
Tasks have durations and dependencies. Backward N3 rules enumerate dependency paths, and scoped collection selects the longest completion time and the tasks that lie on critical paths.
When can the project finish, and which tasks lie on its longest paths?
What we tell Eyeron
The following excerpts use the prefixes declared in the linked source. These are excerpts; the linked file contains the complete program.
# Task durations use the same arbitrary time unit; staffing is unlimited.
:requirements :duration 2 .
# Collect all path durations for a task; its longest path gives its finish.
{
?task :duration ?_ .
(
?candidate {
?task :durationPath (?p ?candidate)
}
?candidates
) log:collectAllIn ?SCOPE .
?candidates list:sort ?sorted .
?sorted list:last ?maxFinish .
} => {
?task :finish ?maxFinish
} .
{ … } => { … } reads “when the left side holds, conclude the right side.”
Names beginning with ? are variables: they stand for the values that make
the conditions match. A backward rule, { … } <= { … }, supplies an answer
when its left-hand goal is called.
What Eyeron concludes
This is an excerpt of the saved conclusions.
:requirements :finish 2 .
:architecture :finish 5 .
:test :projectFinish 23 .
:load_test :schedule (19 21) .
:launch :schedule (22 23) .
:api_design :finish 4 .
The proof, step by step
eyeron -p records why the conclusions follow. This excerpt is one recorded
step from the saved proof:
{ :requirements :finish 2 . }
pe:rule 3;
pe:binding
[ pe:var "_"; pe:value 2 ],
[ pe:var "candidates"; pe:value (2) ],
[ pe:var "maxFinish"; pe:value 2 ],
[ pe:var "sorted"; pe:value (2) ],
[ pe:var "task"; pe:value :requirements ];
pe:uses
{ :requirements :duration 2 . },
{
(?candidate {
:requirements :durationPath (?p ?candidate) .
} (2)) log:collectAllIn ?SCOPE .
},
{ (2) list:sort (2) . },
{ (2) list:last 2 . }.
pe:rule 3 identifies the source rule used by this step. pe:binding records the values substituted for variables; pe:uses lists the premises the step depends on. Those premises have their own supporting steps in the full proof.
Checked: what the report says
The saved check report gives this verdict and these selected conditions:
# checked with obligations: 119 steps, 107 verified, 12 trusted
pe:verdict pe:checkedWithObligations;
pe:condition [ pe:id "C1"; pe:name "resolution"; pe:checked 54; pe:failed 0 ];
pe:condition [ pe:id "C5"; pe:name "re-decision"; pe:checked 65; pe:failed 0 ];
pe:condition [ pe:id "C9"; pe:name "search closure"; pe:checked 13; pe:failed 0 ];
pe:condition [ pe:id "C10"; pe:name "call fidelity"; pe:checked 37; pe:failed 0 ];
Resolution checks that the recorded facts and rule applications match the source program.
Re-decision recomputes the recorded built-in operations.
Search closure checks the supplied evidence for current-scope tests.
Call fidelity checks the answer against the question as it was called.
The verdict is checked with obligations. The result is conditional on the
outstanding obligations listed in the full report; the excerpt does not
discharge them. The report records these obligation kinds: collected.
Try it
eyeron examples/critical-path-schedule.n3
eyeron -p examples/critical-path-schedule.n3
eyeron -c examples/critical-path-schedule.n3
Takeaway
The longest dependency path sets the finish time under the example’s unlimited-staff assumption.