Which tasks determine the launch date?

Follow the longest prerequisite chain, including ties.

program · output · proof · check · playground


The question

A software launch has eleven tasks. Each takes a known time, and some must wait until others are finished: the backend, for example, needs both the API design and the database. Tasks that do not wait on each other can run at the same time; the model assumes enough people and equipment for that. Time units are arbitrary, and no task waits on itself, directly or through others.

The critical path is the chain of tasks where any delay would delay the launch.

When can the launch finish, and which tasks determine that time?


What we tell eyemind: the tasks

fact(task('requirements', 2, []))
fact(task('architecture', 3, ['requirements']))
fact(task('api_design', 2, ['requirements']))
fact(task('database', 4, ['architecture']))
fact(task('backend', 6, ['api_design', 'database']))
fact(task('frontend', 5, ['api_design']))
fact(task('auth', 3, ['architecture']))
fact(task('integration', 4, ['backend', 'frontend', 'auth']))
fact(task('security_review', 3, ['integration']))
fact(task('load_test', 2, ['integration']))
fact(task('launch', 1, ['security_review', 'load_test']))
fact(project_end('launch'))

Each task fact gives a name, a duration, and the list of tasks that must finish first (its prerequisites). The launch is the last task.


What we tell eyemind: the rules

// member(X, List): X is an element of List.
fact(member(X, [X, ..._]))
implied_by(member(X, [_, ...Rest]), member(X, Rest))
// latest_finish(Tasks, Latest): the latest finish among Tasks, 0 for none.
fact(latest_finish([], 0))
implied_by(latest_finish([Task, ...Rest], Latest),
  [schedule(Task, _, Finish), latest_finish(Rest, Remaining), is(Latest, max(Finish, Remaining))])
// A task starts when its prerequisites have all finished.
implied_by(schedule(Task, Start, Finish),
  [task(Task, Duration, Parents), latest_finish(Parents, Start), is(Finish, add(Start, Duration))])
// A critical predecessor of a task finishes exactly when that task starts.
implied_by(critical_predecessor(Task, Parent),
  [task(Task, _, Parents), member(Parent, Parents), schedule(Parent, _, Finish), schedule(Task, Finish, _)])

implies([project_end(Task), schedule(Task, _, Finish)], project_finish(Finish))
// The last task is critical, and so is every critical predecessor of a
// critical task.
implies(project_end(Task), critical_task(Task))
implies([critical_task(Task), critical_predecessor(Task, Parent)], critical_task(Parent))
query(schedule(Task, Start, Finish))
query(project_finish(Finish))
query(critical_task(Task))

What eyemind concludes

// Answers: each instance of a query() that holds.
schedule('requirements', 0, 2)
schedule('architecture', 2, 5)
schedule('api_design', 2, 4)
schedule('database', 5, 9)
schedule('backend', 9, 15)
schedule('frontend', 4, 9)
schedule('auth', 5, 8)
schedule('integration', 15, 19)
schedule('security_review', 19, 22)
schedule('load_test', 19, 21)
schedule('launch', 22, 23)
project_finish(23)
critical_task('launch')
critical_task('security_review')
critical_task('integration')
critical_task('backend')
critical_task('database')
critical_task('architecture')
critical_task('requirements')
task start finish critical
requirements 0 2 yes
architecture 2 5 yes
api_design 2 4  
database 5 9 yes
backend 9 15 yes
frontend 4 9  
auth 5 8  
integration 15 19 yes
security_review 19 22 yes
load_test 19 21  
launch 22 23 yes

The launch finishes at time 23. The seven critical tasks are requirements, architecture, database, backend, integration, security review and launch; their durations, 2 + 3 + 4 + 6 + 4 + 3 + 1, sum to 23.


Why frontend is not critical here

Frontend finishes at time 9, while backend finishes at 15. Integration must wait for backend. A small frontend delay therefore leaves the launch date unchanged, provided frontend still finishes by 15. The same holds for auth (finishing at 8) and load testing (21, while the security review finishes at 22).


The proof, line by line

eyemind --proof writes down how it reached each answer. The whole proof has 78 steps; see the full proof. Here are its claims, all its clauses, and the complete chain of 24 steps behind schedule('backend', 9, 15), which also proves the schedules of the four tasks before it:

// Answers: each instance of a query() that holds.
schedule('requirements', 0, 2)
schedule('architecture', 2, 5)
schedule('api_design', 2, 4)
schedule('database', 5, 9)
schedule('backend', 9, 15)
schedule('frontend', 4, 9)
schedule('auth', 5, 8)
schedule('integration', 15, 19)
schedule('security_review', 19, 22)
schedule('load_test', 19, 21)
schedule('launch', 22, 23)
project_finish(23)
critical_task('launch')
critical_task('security_review')
critical_task('integration')
critical_task('backend')
critical_task('database')
critical_task('architecture')
critical_task('requirements')

// Clauses: the program clauses the steps cite, by clause number.
clause(1, fact(task('requirements', 2, [])))
clause(2, fact(task('architecture', 3, ['requirements'])))
clause(3, fact(task('api_design', 2, ['requirements'])))
clause(4, fact(task('database', 4, ['architecture'])))
clause(5, fact(task('backend', 6, ['api_design', 'database'])))
clause(6, fact(task('frontend', 5, ['api_design'])))
clause(7, fact(task('auth', 3, ['architecture'])))
clause(8, fact(task('integration', 4, ['backend', 'frontend', 'auth'])))
clause(9, fact(task('security_review', 3, ['integration'])))
clause(10, fact(task('load_test', 2, ['integration'])))
clause(11, fact(task('launch', 1, ['security_review', 'load_test'])))
clause(12, fact(project_end('launch')))
clause(13, fact(member(X, [X, ..._0])))
clause(14, implied_by(member(X, [_0, ...Rest]), member(X, Rest)))
clause(15, fact(latest_finish([], 0)))
clause(16, implied_by(latest_finish([Task, ...Rest], Latest), [schedule(Task, _0, Finish), latest_finish(Rest, Remaining), is(Latest, max(Finish, Remaining))]))
clause(17, implied_by(schedule(Task, Start, Finish), [task(Task, Duration, Parents), latest_finish(Parents, Start), is(Finish, add(Start, Duration))]))
clause(18, implied_by(critical_predecessor(Task, Parent), [task(Task, _0, Parents), member(Parent, Parents), schedule(Parent, _1, Finish), schedule(Task, Finish, _2)]))
clause(19, implies([project_end(Task), schedule(Task, _0, Finish)], project_finish(Finish)))
clause(20, implies(project_end(Task), critical_task(Task)))
clause(21, implies([critical_task(Task), critical_predecessor(Task, Parent)], critical_task(Parent)))

// Steps: each goal, what justifies it (a clause, a builtin, a control, an
// absence or a collection), the bindings and the goals it uses.
step(schedule('requirements', 0, 2), clause(17), {Task: 'requirements', Start: 0, Finish: 2, Duration: 2, Parents: []}, [task('requirements', 2, []), latest_finish([], 0), is(2, add(0, 2))])
step(task('requirements', 2, []), clause(1), {}, [])
step(latest_finish([], 0), clause(15), {}, [])
step(is(2, add(0, 2)), 'builtin', {}, [])
step(schedule('architecture', 2, 5), clause(17), {Task: 'architecture', Start: 2, Finish: 5, Duration: 3, Parents: ['requirements']}, [task('architecture', 3, ['requirements']), latest_finish(['requirements'], 2), is(5, add(2, 3))])
step(task('architecture', 3, ['requirements']), clause(2), {}, [])
step(latest_finish(['requirements'], 2), clause(16), {Task: 'requirements', Rest: [], Latest: 2, _0: 0, Finish: 2, Remaining: 0}, [schedule('requirements', 0, 2), latest_finish([], 0), is(2, max(2, 0))])
step(is(2, max(2, 0)), 'builtin', {}, [])
step(is(5, add(2, 3)), 'builtin', {}, [])
step(schedule('api_design', 2, 4), clause(17), {Task: 'api_design', Start: 2, Finish: 4, Duration: 2, Parents: ['requirements']}, [task('api_design', 2, ['requirements']), latest_finish(['requirements'], 2), is(4, add(2, 2))])
step(task('api_design', 2, ['requirements']), clause(3), {}, [])
step(is(4, add(2, 2)), 'builtin', {}, [])
step(schedule('database', 5, 9), clause(17), {Task: 'database', Start: 5, Finish: 9, Duration: 4, Parents: ['architecture']}, [task('database', 4, ['architecture']), latest_finish(['architecture'], 5), is(9, add(5, 4))])
step(task('database', 4, ['architecture']), clause(4), {}, [])
step(latest_finish(['architecture'], 5), clause(16), {Task: 'architecture', Rest: [], Latest: 5, _0: 2, Finish: 5, Remaining: 0}, [schedule('architecture', 2, 5), latest_finish([], 0), is(5, max(5, 0))])
step(is(5, max(5, 0)), 'builtin', {}, [])
step(is(9, add(5, 4)), 'builtin', {}, [])
step(schedule('backend', 9, 15), clause(17), {Task: 'backend', Start: 9, Finish: 15, Duration: 6, Parents: ['api_design', 'database']}, [task('backend', 6, ['api_design', 'database']), latest_finish(['api_design', 'database'], 9), is(15, add(9, 6))])
step(task('backend', 6, ['api_design', 'database']), clause(5), {}, [])
step(latest_finish(['api_design', 'database'], 9), clause(16), {Task: 'api_design', Rest: ['database'], Latest: 9, _0: 2, Finish: 4, Remaining: 9}, [schedule('api_design', 2, 4), latest_finish(['database'], 9), is(9, max(4, 9))])
step(latest_finish(['database'], 9), clause(16), {Task: 'database', Rest: [], Latest: 9, _0: 5, Finish: 9, Remaining: 0}, [schedule('database', 5, 9), latest_finish([], 0), is(9, max(9, 0))])
step(is(9, max(9, 0)), 'builtin', {}, [])
step(is(9, max(4, 9)), 'builtin', {}, [])
step(is(15, add(9, 6)), 'builtin', {}, [])
// … 54 more steps, 78 in total, schedule the remaining tasks, prove the
// finish time, and trace the critical tasks back from the launch.

It has three parts:

The 24 steps say:

  1. Requirements runs from 0 to 2 — by rule 17: it takes 2 (fact 1), it has no prerequisites so it starts at 0 (fact 15), and 0 + 2 = 2.
  2. Requirements takes 2 and needs nothing — fact 1.
  3. The latest finish of no tasks is 0 — fact 15.
  4. 0 + 2 = 2 — builtin.
  5. Architecture runs from 2 to 5 — by rule 17: it waits for requirements.
  6. Architecture takes 3 and needs requirements — fact 2.
  7. The latest finish of ['requirements'] is 2 — by rule 16: requirements finishes at 2, nothing else is in the list, and the larger of 2 and 0 is 2.
  8. max(2, 0) = 2 — builtin.
  9. 2 + 3 = 5 — builtin.
  10. API design runs from 2 to 4 — by rule 17, also waiting for requirements (step 7, reused).
  11. API design takes 2 and needs requirements — fact 3.
  12. 2 + 2 = 4 — builtin.
  13. Database runs from 5 to 9 — by rule 17: it waits for architecture.
  14. Database takes 4 and needs architecture — fact 4.
  15. The latest finish of ['architecture'] is 5 — by rule 16.
  16. max(5, 0) = 5 — builtin.
  17. 5 + 4 = 9 — builtin.
  18. Backend runs from 9 to 15 — by rule 17: it waits for API design and database.
  19. Backend takes 6 and needs API design and database — fact 5.
  20. The latest finish of ['api_design', 'database'] is 9 — by rule 16: API design finishes at 4, the rest of the list at 9, and the larger is 9.
  21. The latest finish of ['database'] is 9 — by rule 16.
  22. max(9, 0) = 9 — builtin.
  23. max(4, 9) = 9 — builtin.
  24. 9 + 6 = 15 — builtin.

The remaining steps work the same way. The critical tasks are traced backward with rules 20, 21 and 18: the launch is critical (it is the project end); the security review is a critical predecessor of the launch, because it is in the launch’s list (fact 13) and finishes at 22, exactly when the launch starts; and so on, back to requirements.


Checked: what the report says

A proof is only worth something if someone else can check it. eyemind -c generates the proof and checks it against the program; --check-proof checks a saved proof. The checker never reasons by itself: it only confirms each step against the program. This is the complete report:

// Answers checked subject to the obligations below.
schedule('requirements', 0, 2)
schedule('architecture', 2, 5)
schedule('api_design', 2, 4)
schedule('database', 5, 9)
schedule('backend', 9, 15)
schedule('frontend', 4, 9)
schedule('auth', 5, 8)
schedule('integration', 15, 19)
schedule('security_review', 19, 22)
schedule('load_test', 19, 21)
schedule('launch', 22, 23)
project_finish(23)
critical_task('launch')
critical_task('security_review')
critical_task('integration')
critical_task('backend')
critical_task('database')
critical_task('architecture')
critical_task('requirements')

// C1-C10: resolution, acyclicity, justification, coverage, re-decision,
// boundary consistency, relevance, witness integrity, search closure and call fidelity.
condition('C1', 'resolution', 'ok', 56)
condition('C2', 'well_founded', 'ok', 78)
condition('C3', 'justification', 'ok', 78)
condition('C4', 'coverage', 'ok', 125)
condition('C5', 're_decision', 'ok', 22)
condition('C6', 'boundary_consistency', 'ok', 0)
condition('C7', 'relevance', 'ok', 97)
condition('C8', 'witness_integrity', 'ok', 0)
condition('C9', 'search_closure', 'ok', 0)
condition('C10', 'call_fidelity', 'ok', 11)

// Obligations: absence, collection or original-call evidence remains unproved.
obligation('call_fidelity', 'original_call', project_finish(23))
obligation('call_fidelity', 'original_call', critical_task('launch'))
obligation('call_fidelity', 'original_call', critical_task('security_review'))
obligation('call_fidelity', 'original_call', critical_task('integration'))
obligation('call_fidelity', 'original_call', critical_task('backend'))
obligation('call_fidelity', 'original_call', critical_task('database'))
obligation('call_fidelity', 'original_call', critical_task('architecture'))
obligation('call_fidelity', 'original_call', critical_task('requirements'))

// Proof statistics: recorded steps and how they were checked.
steps(78)
verified(56)
recomputed(22)
composed(0)
trusted(8)
claims(19)

// This verdict applies to the claims above; it does not establish completeness.
verdict('checked_with_obligations')

Each condition line names a check, says 'ok', and counts what it looked at:

The statistics: 78 steps, 56 verified against the program, 22 recomputed, no boundary steps taken on trust, 19 claims. The verdict is checked with obligations: the schedule, the finish time and the seven critical tasks follow from the program. As the last comment says, this confirms the claims; it does not say the program has no other conclusions. It also establishes only the supplied precedence schedule: shared staffing limits, calendar dates and uncertainty in durations are outside this model.

C10 leaves 8 original-call claims unproved by the available evidence. The verdict is checked with obligations: the recorded derivations are conditional on these call-fidelity obligations. --strict-proof rejects them. The report does not establish answer completeness.


Try it

eyemind examples/critical-path-schedule.js
eyemind --proof examples/critical-path-schedule.js

Or open it in the playground. Change frontend’s duration from 5 to 11. It then finishes at 15, tying backend. Both branches become critical, and the program reports nine critical tasks while the finish time remains 23: frontend and API design join the seven. Make it 12 instead, and frontend alone sets the pace: the finish moves to 24, and backend, database and architecture are no longer critical.


Takeaway

A deadline is set by the longest chain of tasks that wait on each other. Showing that chain step by step tells you which tasks to watch, and which ones have room to slip.